Roadwork to start on Platteview Road from 87th to 120th Street

Sarpy County

Roadwork to start on Platteview Road from 87th to 120th Street

Date: 
July 19, 2018

On July 23, crews will begin a mill-and-overlay project on Platteview Road from 87th Street to 120th Street. The work will continue through Aug. 15, depending on weather.

During the project, crews will be milling off 1 inch of the top layer of the road surface, repairing the road base and applying a new 3-inch layer of asphalt.

Platteview Road will be open to traffic during the construction process, but portions of the road will be limited to a single lane. Pilot cars will lead traffic through the restricted areas.

Drivers should expect delays and use caution through the area. We are asking drivers to use an alternative route, if possible.

See other county road closures.